The Township is also continuing work on stormwater projects outlined in the 2023 budget.
The Township’s Public Works Department is working to replace failing pipe on Andrew Drive. Our crew has been working diligently to address these sections of pipe.
The Bolmar Street Culvert Replacement Project, being completed by G&B Construction, began work on June 5, 2023. The construction requires the road to be closed and all traffic detoured around the work. G&B Construction posted the detour the week of May 29, 2023. Sartomer Inc, A. Duie Pyle Inc, and Lewis Automotive will be open and able to be accessed from the northern side of the project at the East Nields Street intersection. The project is planned to be completed by the end of the summer. For additional information on this project, please visit the West Goshen Township website.
In 2023, the Township is targeting to complete repair work for a culvert on Matlack Street and targeted corrugated metal pipe replacements. The Township also recently complete a Regional Stormwater Feasibility Study that is available on the Township website. A link is available in an earlier story. These projects are being funded through the funds received through the American Rescue Plan Act of 2021. Additionally, the Township is continuing to complete design work for projects outlined in our Pollution Reduction Plan approved by the PA Department of Environmental Protection. Please watch the West Goshen Township website for additional information.